15 men working 8 hours per day complete a piece of work in 18 days. To…
2024
15 men working 8 hours per day complete a piece of work in 18 days. To complete the same work in 6 days, working 12 hours a day, the number of men required will be:
Answer: D. 30 men
- A.
24 men
- B.
26 men
- C.
28 men
- D.
30 men
Attempted by 18 students.
Show answer & explanation
Correct answer: D
Loading lesson…